Here's a view from one side to the other.
Saturday, June 30, 2007
Digging Day #4
Digging Day #4 was a big day. The crew completed removing most of the dirt and made the walls vertical so that they could begin adding the footer frames. Things are really beginning to take shape.
Friday, June 29, 2007
Digging Day #3
Thursday, June 28, 2007
Digging Day #2
Wednesday, June 27, 2007
Digging Day #1
Sunday, June 24, 2007
Demolition Day 3
DONE! It's all torn down, sorted into piles and awaiting removal. After the pile of rubble is removed, the excavation work will begin for the new foundation & new basement.
Hello right back at you.
A "HI" view from the second floor.
No work is planned for the weekend, but these pictures show where things stand for now.
Hey, I can see the neighbor's house from here...
No work is planned for the weekend, but these pictures show where things stand for now.Friday, June 22, 2007
Demolition Day 2
As you can see, Day #2 was pretty busy. The old addition has been reduced to just the concrete floor. Here, take a look...
Thursday, June 21, 2007
Demolition Day 1
Well, as you can see the demolition work is underway! Most of the roof has been removed and part of the chimney. There's still a lot to do, but the crew will make quick work of it.
Tuesday, June 19, 2007
Prep for Demolition
Welcome Back! We've started the demolition part of the project. However, the first thing we needed to do was block off the walkway between the kitchen and the existing addition. The second, was to get the AC compressor moved so we can stay cool throughout the construction process. Here's some shots to show the progress.
This is where the AC compressor will be moving too.
And here, it's been moved (excellent work, Pete!).
This is the outside of the family room, before....
And here's the door removed....
And it's been re-hung in the walkway between the kitchen and family room. Time to tear down that family room!
Sunday, June 10, 2007
The "BEFORE" Picture
The Backyard!