What a difference a week makes! As you can see most of the framing on the addition is about done. The first & second floors are framed, the windows installed, and we've started working the details for interior walls.
This is a view of the Master Bathroom. To eliminate wasted space, created by a door swing, we're planning a 30" pocket door set off center so we have plenty of wall space for towels and such next to the tiled shower.
Here's a view from the back yard. We've got just short of 30' from the back of the house to the back fence. So there's room for having outside fun!

This is a view from the far corner of the Master Bath. The framing in the center is temporary, for support only, and there will be a 6'x16' walk-in closet running half the length of the house against the existing brick wall.

Here's a view from what will be the inside of the walk-in closet.

And another view from the outside left corner looking back toward the existing house.